Wednesday · 09 April
Today on site
Five tasks to complete. All drawings updated to revision 04.
Hauptstraße 12, Berlin
Today's tasks
Drawings — rev 04
Tap to enlarge
Electrical layout
E-10.pdf
Lighting circuit
E-11.pdf
Junction box plan
E-12.pdf
From the PM
Plasterers arrive Monday 7:30. All first-fix electrical must be tested and signed off by Friday EOD. Use junction box plan v04 — the bedroom 2 location moved 30cm.
L. Voss · 08 Apr · 17:42
Materials needed today
- 20m × 2.5mm² cablein van
- 6 × junction boxeson site
- Heating loop testerin van
- Cable clips (200)needed
Site notes
Discovered old gas pipe behind kitchen wall — capped, photo uploaded.
Yesterday
Bedroom 2 socket layout works better against the south wall.
2 days ago
Deliveries
- in transit
Cable clips (200)
Today · 14:00
- scheduled
Worktop — Calacatta
Apr 22 · AM
- scheduled
Oak parquet
Apr 26