Wednesday · 09 April

Today on site

Five tasks to complete. All drawings updated to revision 04.

Hauptstraße 12, Berlin

Today's tasks

Drawings — rev 04

Tap to enlarge

Updated yesterday

Electrical layout

E-10.pdf

Lighting circuit

E-11.pdf

Junction box plan

E-12.pdf

From the PM

Plasterers arrive Monday 7:30. All first-fix electrical must be tested and signed off by Friday EOD. Use junction box plan v04 — the bedroom 2 location moved 30cm.

L. Voss · 08 Apr · 17:42

Materials needed today

  • 20m × 2.5mm² cablein van
  • 6 × junction boxeson site
  • Heating loop testerin van
  • Cable clips (200)needed

Site notes

  • Discovered old gas pipe behind kitchen wall — capped, photo uploaded.

    Yesterday

  • Bedroom 2 socket layout works better against the south wall.

    2 days ago

Deliveries

  • Cable clips (200)

    Today · 14:00

    in transit
  • Worktop — Calacatta

    Apr 22 · AM

    scheduled
  • Oak parquet

    Apr 26

    scheduled